BAM Nuttall Blockade
During week 47 & week 48 we completed a 9 day blockade with 9 RRVs, installing 370m of King Post Piling and installation.
This included the re-grading of the embankment existing retaining wall as part of the works to prevent land slips in this area which has been a reoccurring issue for several years.
All works successfully completed, following weeks of planning.